permitsolutions.io / projects / PS-24-1230
Projects
·
PS-24-1230
Wabash River Crossing
Funding partner
NTIA BEAD
Funding program
Grid Resilience
NEPA determination
EA
Program manager
MR
Maria Reyes
Submitted
May 1, 2026
Monitoring agency reviews
0 open itemsNEPA pathway
EA
PS-24-1230 · Grid Resilience
5 of 5 NEPA & permit reviews still in flight for this project.
Project intake checklist
5 / 5 cleared
✓
Route geometry & applicant intake accepted
Heartland Fiber Co-op · 8 mi · submitted May 1, 2026
✓
GIS environmental screen completed
Eight authoritative layers screened for Wabash River Crossing, IN.
✓
NEPA pathway documented
EA recorded for PS-24-1230.
✓
Agency reviews routed
5 NEPA & permit reviews open across 4 agencies.
✓
Program manager assigned
Maria Reyes · portfolio owner for PS-24-1230.
Project workflow
-
Intake reviewApplicant package & route geometry
-
GIS screeningEnvironmental overlay analysis
-
NEPA determinationCatEx, EA, or EIS pathway
-
NEPA & permit reviewsAgency-specific workflows
-
AuthorizationNEPA clearance & permit issuance
NEPA & review timeline
Day 25 / 90
NEPA & review timeline
65 days to target NTP
Received May 1, 2026
Due Target NTP · PS-24-1230
Funding program
PS-24-1230 · federal nexus through Grid Resilience funding administered by NTIA BEAD
Program
Grid Resilience
Funding partner
NTIA BEAD
Subgrantee
Heartland Fiber Co-op
Estimated allocation
$560,000 estimated · 8 mi
Authorization milestones
Intake accepted
May 1, 2026
Environmental review initiated
May 1, 2026
NEPA clearance issued
Pending
Notice to Proceed eligible
—
Eligibility checklist
- ✓ Heartland Fiber Co-op enrolled as Grid Resilience subgrantee
- ✓ Project type eligible under Grid Resilience rules
- ✓ Environmental review initiated prior to NTP
- Draw request aligned to authorization milestone
Program requirements
- NEPA clearance required before Notice to Proceed for PS-24-1230
- 5 triggered NEPA & permit reviews must reach authorization
- Quarterly SAR reporting to NTIA BEAD
- Administrative record export on project closeout
Environmental layer screening · PS-24-1230
8 mi route · Wabash River Crossing, IN| Layer | Source | Flags | Status | Triggered review |
|---|---|---|---|---|
| NWI Wetlands | USFWS NWI | 7 | Flagged | Section 404 – Wetlands |
| Critical Habitat | USFWS IPaC | 6 | Flagged | Section 7 – ESA Consultation |
| Historic Properties | SHPO / NRHP | 6 | Flagged | Section 106 – Historic Review |
| BLM-Managed Lands | BLM SMA | 5 | Flagged | Right-of-Way Grant |
| Coastal Zone | State CZM | — | Clear | — |
CatEx not qualified · EA required
PS-24-1230 · Grid ResilienceWabash River Crossing did not qualify for a categorical exclusion. Extraordinary circumstances or project scope require an Environmental Assessment.
CEQ Categorical Exclusion Database
Categories sourced from the CEQ Categorical Exclusion Database (DOC/NTIA NEPA procedures) — 1 category matched for this project.
CatEx C-8 — Aerial/Buried Utility & Communication Systems
Acquisition, installation, reconstruction, repair by replacement, and operation of aerial or buried utility (e.g., water, sewer, electrical), communication (e.g., fiber optic cable, data processing cable and similar electronic equipment), and security systems that use existing rights-of-way, easements, grants of license, distribution systems, facilities, or similar arrangements.
CEQ ID: NTIA---3-30
Extraordinary circumstances identified during GIS screening
Extraordinary circumstances screening
- ✗ Wetland or floodplain impacts exceed CatEx thresholds
- ✗ Effects on federally listed species or critical habitat
- ✗ Navigable water crossing requires individual evaluation
- ✓ No disproportionate impact to EJ communities
- ✓ No hazardous materials or contaminated sites on route
NEPA documents
Permits · PS-24-1230
0 approved · 5 pendingTotal
5
Approved
0
In review
4
Action required
0
| Permit | Agency | Approval status | Submitted | Assigned to |
|---|---|---|---|---|
| Section 404 – Wetlands | USACE | In Review | May 5, 2026 | Phuong Nguyen |
| Section 10 – Navigable Waters | USACE | In Review | May 5, 2026 | Phuong Nguyen |
| Section 7 – ESA Consultation | USFWS | In Review | May 8, 2026 | Assign |
| Section 106 – Historic Review | SHPO | Pending | May 8, 2026 | Michael Brown |
| Right-of-Way Grant | BLM | In Review | May 10, 2026 | Diana Ortiz |
By agency
| Agency | Permits | Approved | In review |
|---|---|---|---|
| USACE | 2 | 0 | 2 |
| USFWS | 1 | 0 | 1 |
| SHPO | 1 | 0 | 0 |
| BLM | 1 | 0 | 1 |
Agency Data Feeds · PS-24-1230
3 of 5 connected
USFWS
IPaC Species Data
Live
24 rec · 2h ago
USACE
ePermit Tracker
Live
8 rec · 18h ago
SHPO
Section 106
Pending
BLM
LR2000 Land Records
Not connected
State DNR
Environmental Clearance
Live
3 rec · 6h ago
USFWS · IPaC Species Data
Last sync: 2h ago · 24 records
| Northern long-eared bat | Threatened |
| Red-cockaded woodpecker | Endangered |
| Virginia big-eared bat | Endangered |
| Critical habitat overlap | 0.8 acres |
| Action area buffer | 1.0 mi |
USACE · ePermit Tracker
Last sync: 18h ago · 8 records
| Jurisdictional wetlands | 0.3 acres |
| NWP 12 eligibility | Likely eligible |
| Delineation report | Pending |
| Permit determination | In review |
SHPO · Section 106
No sync data
| Phase I survey | Received |
| Historic properties | None identified |
| Determination | Pending (30 days) |
BLM · LR2000 Land Records
No sync data
No data feed configured for this project. Set up connection
State DNR · Environmental Clearance
Last sync: 6h ago · 3 records
| State sensitive areas | Outside boundary |
| State permit required | No |
| Clearance letter | Issued May 30 |
Inter-agency thread · PS-24-1230
5 messages · 5 participantsSC
Sarah Chen
USFWS
May 28, 2:14 PM
Completed IPaC species screening for PS-24-1230. Found 3 listed species in the action area — northern long-eared bat, Indiana bat, and Virginia big-eared bat. Recommending informal consultation pathway based on preliminary effects analysis.
MR
Marcus Rivera
USACE
May 28, 3:41 PM
USACE Louisville District confirms 0.3 acres of jurisdictional wetland within the proposed alignment. NWP 12 likely applies but we need the delineation report before we can issue verification. Can the applicant expedite the wetland delineation submittal?
AF
Dr. Angela Fournet
KY SHPO
May 29, 9:07 AM
Section 106 review initiated. Phase I cultural resources survey report received and under review. Preliminary finding: no historic properties affected within the APE. Expect formal determination within 30 days.
SC
Sarah Chen
USFWS
May 29, 11:30 AM
@Marcus — FYI, the bat habitat buffer overlaps the same wetland area you flagged. We should coordinate timing on the NWP verification and informal consultation to avoid duplicate field visits. Happy to schedule a joint site review if that helps.
JT
James Thompson
State DNR
May 30, 8:22 AM
State environmental clearance pre-screening complete. Project falls outside any state-managed sensitive area — no additional state permit required. Issuing clearance letter today.
STEP 1 OF 7