Projects · PS-24-1230

Wabash River Crossing

Heartland Fiber Co-op · Grid Resilience · 8 mi · Wabash River Crossing, IN

Funding partner
NTIA BEAD
Funding program
Grid Resilience
NEPA determination
EA
Program manager
MR Maria Reyes
Submitted
May 1, 2026
Open items
0
Project status
In Review
NEPA pathway
EA
Program manager
Maria Reyes
Program
Grid Resilience
Funding partner
NTIA BEAD
Estimated allocation
$560,000 estimated · 8 mi
Reporting
Quarterly SAR · NTIA schema
Layers scanned
5
Layer flags
24
Route length
8 mi
Triggered reviews
5
NEPA pathway
EA
Determination
Environmental Assessment required
CatEx categories
1
Supporting documents
1
Total permits
5
Approved
0
In review
4
Action required
0
Data feeds
3 / 5
Participants
5
Agencies
4
Messages
5
Shared files
6

Monitoring agency reviews

0 open items
NEPA pathway
EA
PS-24-1230 · Grid Resilience

5 of 5 NEPA & permit reviews still in flight for this project.

Project intake checklist

5 / 5 cleared
Route geometry & applicant intake accepted
Heartland Fiber Co-op · 8 mi · submitted May 1, 2026
GIS environmental screen completed
Eight authoritative layers screened for Wabash River Crossing, IN.
NEPA pathway documented
EA recorded for PS-24-1230.
Agency reviews routed
5 NEPA & permit reviews open across 4 agencies.
Program manager assigned
Maria Reyes · portfolio owner for PS-24-1230.

Project workflow

  • Intake review
    Applicant package & route geometry
  • GIS screening
    Environmental overlay analysis
  • NEPA determination
    CatEx, EA, or EIS pathway
  • NEPA & permit reviews
    Agency-specific workflows
  • Authorization
    NEPA clearance & permit issuance

NEPA & review timeline

Day 25 / 90
NEPA & review timeline 65 days to target NTP
Received May 1, 2026 Due Target NTP · PS-24-1230

Funding program

PS-24-1230 · federal nexus through Grid Resilience funding administered by NTIA BEAD

Program
Grid Resilience
Funding partner
NTIA BEAD
Subgrantee
Heartland Fiber Co-op
Estimated allocation
$560,000 estimated · 8 mi

Authorization milestones

Intake accepted May 1, 2026
Environmental review initiated May 1, 2026
NEPA clearance issued Pending
Notice to Proceed eligible

Eligibility checklist

  • Heartland Fiber Co-op enrolled as Grid Resilience subgrantee
  • Project type eligible under Grid Resilience rules
  • Environmental review initiated prior to NTP
  • Draw request aligned to authorization milestone

Program requirements

  • NEPA clearance required before Notice to Proceed for PS-24-1230
  • 5 triggered NEPA & permit reviews must reach authorization
  • Quarterly SAR reporting to NTIA BEAD
  • Administrative record export on project closeout

Environmental layer screening · PS-24-1230

8 mi route · Wabash River Crossing, IN
Layer Source Flags Status Triggered review
NWI Wetlands USFWS NWI 7 Flagged Section 404 – Wetlands
Critical Habitat USFWS IPaC 6 Flagged Section 7 – ESA Consultation
Historic Properties SHPO / NRHP 6 Flagged Section 106 – Historic Review
BLM-Managed Lands BLM SMA 5 Flagged Right-of-Way Grant
Coastal Zone State CZM Clear
Loading layers…
Screening route…

CatEx not qualified · EA required

PS-24-1230 · Grid Resilience

Wabash River Crossing did not qualify for a categorical exclusion. Extraordinary circumstances or project scope require an Environmental Assessment.

CEQ Categorical Exclusion Database
Categories sourced from the CEQ Categorical Exclusion Database (DOC/NTIA NEPA procedures) — 1 category matched for this project.
CEQ Database
CatEx C-8 — Aerial/Buried Utility & Communication Systems
Acquisition, installation, reconstruction, repair by replacement, and operation of aerial or buried utility (e.g., water, sewer, electrical), communication (e.g., fiber optic cable, data processing cable and similar electronic equipment), and security systems that use existing rights-of-way, easements, grants of license, distribution systems, facilities, or similar arrangements.
CEQ ID: NTIA---3-30
Extraordinary circumstances identified during GIS screening
Not qualified

Extraordinary circumstances screening

  • Wetland or floodplain impacts exceed CatEx thresholds
  • Effects on federally listed species or critical habitat
  • Navigable water crossing requires individual evaluation
  • No disproportionate impact to EJ communities
  • No hazardous materials or contaminated sites on route

NEPA documents

EA scoping notice · PS-24-1230
Draft · Heartland Fiber Co-op
420 KB

Permits · PS-24-1230

0 approved · 5 pending
Total
5
Approved
0
In review
4
Action required
0
Permit Agency Approval status Submitted Assigned to
Section 404 – Wetlands USACE In Review May 5, 2026 Phuong Nguyen
Section 10 – Navigable Waters USACE In Review May 5, 2026 Phuong Nguyen
Section 7 – ESA Consultation USFWS In Review May 8, 2026 Assign
Section 106 – Historic Review SHPO Pending May 8, 2026 Michael Brown
Right-of-Way Grant BLM In Review May 10, 2026 Diana Ortiz

By agency

Agency Permits Approved In review
USACE 2 0 2
USFWS 1 0 1
SHPO 1 0 0
BLM 1 0 1

Agency Data Feeds · PS-24-1230

3 of 5 connected
USFWS
IPaC Species Data
Live
24 rec · 2h ago
USACE
ePermit Tracker
Live
8 rec · 18h ago
SHPO
Section 106
Pending
BLM
LR2000 Land Records
Not connected
State DNR
Environmental Clearance
Live
3 rec · 6h ago
USFWS · IPaC Species Data Last sync: 2h ago · 24 records
Northern long-eared bat Threatened
Red-cockaded woodpecker Endangered
Virginia big-eared bat Endangered
Critical habitat overlap 0.8 acres
Action area buffer 1.0 mi
USACE · ePermit Tracker Last sync: 18h ago · 8 records
Jurisdictional wetlands 0.3 acres
NWP 12 eligibility Likely eligible
Delineation report Pending
Permit determination In review
SHPO · Section 106 No sync data
Phase I survey Received
Historic properties None identified
Determination Pending (30 days)
BLM · LR2000 Land Records No sync data
No data feed configured for this project. Set up connection
State DNR · Environmental Clearance Last sync: 6h ago · 3 records
State sensitive areas Outside boundary
State permit required No
Clearance letter Issued May 30

Inter-agency thread · PS-24-1230

5 messages · 5 participants
SC
Sarah Chen USFWS May 28, 2:14 PM
Completed IPaC species screening for PS-24-1230. Found 3 listed species in the action area — northern long-eared bat, Indiana bat, and Virginia big-eared bat. Recommending informal consultation pathway based on preliminary effects analysis.
MR
Marcus Rivera USACE May 28, 3:41 PM
USACE Louisville District confirms 0.3 acres of jurisdictional wetland within the proposed alignment. NWP 12 likely applies but we need the delineation report before we can issue verification. Can the applicant expedite the wetland delineation submittal?
AF
Dr. Angela Fournet KY SHPO May 29, 9:07 AM
Section 106 review initiated. Phase I cultural resources survey report received and under review. Preliminary finding: no historic properties affected within the APE. Expect formal determination within 30 days.
SC
Sarah Chen USFWS May 29, 11:30 AM
@Marcus — FYI, the bat habitat buffer overlaps the same wetland area you flagged. We should coordinate timing on the NWP verification and informal consultation to avoid duplicate field visits. Happy to schedule a joint site review if that helps.
JT
James Thompson State DNR May 30, 8:22 AM
State environmental clearance pre-screening complete. Project falls outside any state-managed sensitive area — no additional state permit required. Issuing clearance letter today.